STORY
Our company undertook the project of M/V Atlantic Monaco container ship, following assignment by Carell S.A. and Shiprep Management companies. All works were carried out on the internal areas of the vessel, while it was dry docked and it took a total of 25 days for their completion. More specifically, Alkyonis undertook and implemented the following works:
- Modulation & restoration of cabin areas with B15 wall & ceiling panels
- Thermal insulation of piping systems in E/R
- Insulation of auxiliary engines’ exhausts
- Thermal insulation of surfaces in cabin areas
- Vinyl floor installation in cabin areas
SPEC
Vessel name
M/V Atlantic Monaco
Vessel type
Container Ship
Shipyard
Onex Syros Shipyards
Year of build
2008